What’s the quantity of steel, cement and sand for 1100 sqft area of an RCC roof? 1100 sq ft concrete slab cost in india and rcc. calculate quantity of sariya, sand cement and aggregate in roof slab. And also know about construction cost of RCC slab of 1100 square feet
1100 sq ft concrete slab cost in india and rcc. Construction cost of RCC slab for 1100 square feet and 1100 sq ft concrete slab cost in india and for the roof cast of 1100 square feet building roof slab, you have require Steel bar ,sand, cement and aggregate.
💐—- WATCH THIS VIDEO—💐
What’s the quantity of steel, cement and sand for 1100 sqft area of an RCC roof?, quantity of cement, sand, Steel bar and aggregate required ,you know that for the casting of roof slab we used M20 mix concrete.1100 sq ft concrete slab cost in india and rcc
Construction cost of RCC slab of 1100 square feet
In M20 mix concrete M is stand for mix and numerical figure 20 is stand for characteristic of compressive strength 20N/mm2 after mixing and casting of roof slab, quantity of material in slab formation it calculated by M20 mix in which ratio of cement, sand and aggregate is 1: 1.5 :3
M20 mix Ratio is 1 : 1.5 : 3 in which one part is cement 1. 5 part is sand and 3 part is aggregate and
Total proportion = 1+1.5+3=5.5
Part of cement = 1/5.5
Part of sand = 1.5/5.5
Part of aggregate = 3/5.5
Steel required for 1100 sq ft slab
Steel bar calculation in roof slab reinforcement we provide there is a two types of Steel bar used main bar and cross bar. And know about roof slab Steel calculation
1) Main bar:- main bar is also called as shortist span bar usually used at bottom of slab having spacing 4 inch between the two bar.
Main bar is also called tension Steel because it is provided in tension zone of roof slab in bottom having tensile strength of steel is enough yield strength and ultimate tensile strength.
We should use hi tensile steel in main bar Fe550D. sufficient amount of main bar used in shorter direction having 10 mm or 12 mm dia of Steel bar according to roof slab reinforcement.
2) Cross bar:- cross bar is also called as longer span bar or distribution bar or cross bar mainly used at top of the main bar in compression zone of slab, cross bar usually dia of 8mm or 10 mm bar Steel bar used in longer direction according to roof slab reinforcement.
Roof slab casting is process of laying And putting concrete mix in horizontal direction and structure over brickwork. Cast of roof slab reinforcement main bar and cross bar in distributed over shuttering areas of roof slab and then we put concrete mix of M20 or m25 grade of concrete that is known as roof slab casting.
Given dimensions of roof slab thickness ranging between 4 inch to 6 inch but in this calculation we take roof slab thickness is 5 inch
Roof slab thickness =5″
Length of slab =44′
Breadth of slab=25′
Area of slab =25’×44’=1100 sqft
M -20 -mix =1:1.5:3 (concrete)
Volume Calculation of concrete
1) wet volume = Area × thicknessof slab
Wet volume of concrete = 1100 sqft× 5″
Wet volume = 1100sqft × 5/12′
Wet volume = 458.33 cft
If you want to convert it into cubic metre you should divide by 35.3147
1m3 =35.3147 cft
Wet volume = 458.33 /35.3147=12.98 m3
2) Dry volume of concrete
we know that wet volume have voids and pore which filled with water and bubbles it can be remove by vibrator or compressor machine so more quantity of material is required.
dry volume means mixture of cement sand and aggregates concrete in dry condition have more voids and pores that are evaporated in wet condition and volume is decrease by 54 percent in wet condition and volume of dry concrete in increased by 54% , so we can multiply 1.54 in wet volume to calculate dry volume
Dry volume =1.54 × 12.98 m3
Dry volume of concrete = 19.98 m3
Roof slab steel calculation and weight calculation of Steel quantity of steel required in roof slab is about 0.5℅ to 1% of dry volume then average is 0.75% of dry volume
Weight of steel = 0.75%of dry volume × density of steel
Density of steel is=7850 kg/m3
Weight = 0.75/100× 19.98m3 ×7850kg/m3
Weight = 1177 kg =1.177 tons
Weight of Steel bar is require for 1100 square feet Roof slab= 1177 Kg
1177 Kg Steel required for roof casting of 1100 sq ft rcc slab
If Market rate of steel bar is 60 rupees per kg then
total cost of Steel bar =1177 × rs 60
Total cost = Rs 70600
Sand required for 1100 sq ft slab
In M20 ratio of sand cement and aggregate is 1:1.5:3 ,in this ratio 1.5 part is sand
Total proportion =1+1.5+3=5.5
Volume of sand in cft
Volume =1.5 /5.5 ×19.98 ×35.3147 cft
Volume of sand =192.43 cft
192.43 cft volume of sand required for roof casting of 1100 sq ft rcc slab.
If market rate of 60 rupees per CFT then total cost of quantity of sand
Total cost = rs 60 × 192.43 = rs 11546
Cement required for 1100 sq ft slab
Cement calculation in M20 mix 1 part is cement quantity
Weight of cement=1/5.5 × dry volume in m3× density of cement
Density of cement=1440 kg/m3
Weight of cement =1/5.5 × 19.98 m3 ×1440 kg/m3
Weight of cement = 5231 Kg
1 bag cement =50kg
No.of bags = 5231/50
Cement bags =104.62
104.62 number of cement bag required for roof casting of 1100 sq ft RCC slab
If market rate of cement is 350 rupees per bags then total cost
Total cost = 105 ×rs 350
Total cost of cement = Rs 36750
Aggregate required for 1100 sq ft slab
Aggregate Calculation in M20 mix there is 3 part of aggregate quantity
Volume of aggregate = 3/5.5 × dry volume in CFT
Volume = 3/5.5 ×19.98×35.3147 cft
Volume of aggregate = 385 cft
385 cft volume of aggregate is required for Roof casting of 1100 sq ft RCC slab.
If market rate of aggregate is 70 rupees per CFT then total cost of aggregate
Total cost = rs 70 × 385
Total cost of aggregate = rs 26950
Total construction cost of 1100 sq ft rcc slab
● total cost of material:-
Cost of steel = rs 70600
Cost of cement = rs 36750
Cost of sand = rs 11546
Cost of stone = rs 26950
Labour charge and machine cost = rs 50000 (approx)
Total cost = Rs 195846
1100 sq ft concrete slab cost in India is rs 195846
Steel 1177 Kg, Cement 105 bags, sand 192.43 cft and Aggregate 385 cft material are required for roof casting of 1100 sq ft rcc slab.
◆You Can Follow me on Facebook and Subscribe our Youtube Channel
You should also visits:-
1)what is concrete and its types and properties
2) concrete quantity calculation for staircase and its formula
●Now your turn:- please like and comment it above this post, if you have any query and question about this please you will ask, thanks a”lot.