How many yards of concrete do I need for 1000 sq ft
Concrete ready mix made of blended mix of Portland cement, sand gravel and other approved ingredient, generally, dry ready mix concrete are available in different bag size and weight condition like 40lb bag, 50lb, 60lb bag, 80lb bag 90lb bag and you can also prepared concrete mix by manually by mixing of Portland cement, sand and gravel with water in 1:2:3 mix ratio (1 part of cement mix with 2 parts of sand and 3 parts of stone or gravel).
Weight of Ready mix concrete in dry condition is about 133 lbs per cubic foot, 3600 lbs per cubic yard, or 2136 kg per cubic meter. The weight of concrete is determined by its density, which can vary based on the amount of aggregate, water, and air in the mix.
In United States, based on Imperial measurement system, 1 cubic yard is unit of measurement of volume represented by 3 feet long by 3 feet wide by 3 feet depth (3’×3’×3′ = 27 cubic feet), so 1 cubic yard is equal to 27 cubic feet.
How many yards of concrete do I need for 1000 sq ft slab vary depending on the type of concrete mix you choose for your project and thickness of slab. A typical effective concrete slab will at least have a 4″ thickness and 5″ -6″ is apply in certain conditions.
How many yards of concrete do I need for 1000 sq ft
For a 4 inch slab, there is the quick rule of thumb and guidelines is to divide the given square footage by 80, and that will give you the amount of yards of concrete needed. For example if your 1000 square feet slab, you would need approximately 12.5 yards of concrete.
For a 5 inch slab, there is the quick rule of thumb and guidelines is to divide the given square footage by 65, and that will give you the amount of yards of concrete needed. For example if your 1000 square feet slab, you would need approximately 15.5 yards of concrete.
As per thumb rule and guidelines, for 1000 sq. ft. or (25 ×40) slab at 4 inch thickness, you will need approximately 12.5 cubic yards of concrete and at 5 inch thickness 15.5 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 1000÷80= 12.5 cu. yd. and 2) at 5 inch thickness, concrete quantity = 1000÷65= 15.5 cubic yards.
◆You Can Follow me on Facebook and
Subscribe our Youtube Channel
How many yards of concrete do I need for 1100 sq ft
As per thumb rule and guidelines, for 1100 sq. ft. slab at 4 inch thickness, you will need approximately 14 cubic yards of concrete and at 5 inch thickness 17 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 1100÷80= approx 1 4 cu. yd. and 2) at 5 inch thickness, concrete quantity = 1100÷65= approx 17 cubic yards.
How many yards of concrete do I need for 1200 sq ft
As per thumb rule and guidelines, for 1200 sq. ft. or (30×40) slab at 4 inch thickness, you will need approximately 15 cubic yards of concrete and at 5 inch thickness 18.5 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 1200÷80= approx 15 cu. yd. and 2) at 5 inch thickness, concrete quantity = 1200÷65= approx 18.5 cubic yards.
How many yards of concrete do I need for 1600 sq ft
As per thumb rule and guidelines, for 1600 sq. ft. or (40×40) slab at 4 inch thickness, you will need approximately 20 cubic yards of concrete and at 5 inch thickness 25 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 1600÷80= approx 20 cu. yd. and 2) at 5 inch thickness, concrete quantity = 1600÷65= approx 25 cubic yards.
How many yards of concrete do I need for 2000 sq ft
As per thumb rule and guidelines, for 2000 sq. ft. or (40×50) slab at 4 inch thickness, you will need approximately 25 cubic yards of concrete and at 5 inch thickness 31 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 2000÷80= approx 25 cu. yd. and 2) at 5 inch thickness, concrete quantity = 2000÷65= approx 31 cubic yards.
How many yards of concrete do I need for 2400 sq ft
As per thumb rule and guidelines, for 2400 sq. ft. or (40×60) slab at 4 inch thickness, you will need approximately 30 cubic yards of concrete and at 5 inch thickness 37 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 2400÷80= approx 30 cu. yd. and 2) at 5 inch thickness, concrete quantity = 2400÷65= approx 37 cubic yards.
How many yards of concrete do I need for 2500 sq ft
As per thumb rule and guidelines, for 2500 sq. ft. or (50×50) slab at 4 inch thickness, you will need approximately 32 cubic yards of concrete and at 5 inch thickness 39 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 2500÷80= approx 32 cu. yd. and 2) at 5 inch thickness, concrete quantity = 2500÷65= approx 39 cubic yards.
How many yards of concrete do I need for 3000 sq ft
As per thumb rule and guidelines, for 3000 sq. ft. or (50×60) slab at 4 inch thickness, you will need approximately 38 cubic yards of concrete and at 5 inch thickness 46 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 3000÷80= approx 38 cu. yd. and 2) at 5 inch thickness, concrete quantity = 3000÷65= approx 46 cubic yards.
How many yards of concrete do I need for 3000 sq ft
How many yards of concrete do I need for 4000 sq ft
As per thumb rule and guidelines, for 4000 sq. ft. slab at 4 inch thickness, you will need approximately 50 cubic yards of concrete and at 5 inch thickness 62 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 4000÷80= approx 50 cu. yd. and 2) at 5 inch thickness, concrete quantity = 4000÷65= approx 62 cubic yards.
How many yards of concrete do I need for 5000 sq ft
As per thumb rule and guidelines, for 5000 sq. ft. slab at 4 inch thickness, you will need approximately 63 cubic yards of concrete and at 5 inch thickness 77 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 5000÷80= approx 63 cu. yd. and 2) at 5 inch thickness, concrete quantity = 5000÷65= approx 77 cubic yards.
How many yards of concrete do I need for 144 sq ft
As per thumb rule and guidelines, for 144 sq. ft. or (12×12) slab at 4 inch thickness, you will need approximately 1.8 cubic yards of concrete and at 5 inch thickness 2.2 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 144÷80= approx 1.8 cu. yd. and 2) at 5 inch thickness, concrete quantity = 144÷65= approx 2.2 cubic yards.
How many yards of concrete do I need for 160sq ft
As per thumb rule and guidelines, for 160 sq. ft. or (10×16) slab at 4 inch thickness, you will need approximately 2 cubic yards of concrete and at 5 inch thickness 2.5 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 160÷80= approx 2 cu. yd. and 2) at 5 inch thickness, concrete quantity = 160÷65= approx 2.5 cubic yards.
How many yards of concrete do I need for 300 sq ft
As per thumb rule and guidelines, for 300 sq. ft. or (15×20) slab at 4 inch thickness, you will need approximately 3.75 cubic yards of concrete and at 5 inch thickness 4.6 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 300÷80= approx 3.75 cu. yd. and 2) at 5 inch thickness, concrete quantity = 300÷65= approx 4.6 cubic yards.
How many yards of concrete do I need for 400 sq ft
As per thumb rule and guidelines, for 400 sq. ft. or (20×20) slab at 4 inch thickness, you will need approximately 5 cubic yards of concrete and at 5 inch thickness 6.25 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 400÷80= approx 5 cu. yd. and 2) at 5 inch thickness, concrete quantity = 400÷65= approx 6.25 cubic yards.
How many yards of concrete do I need for 500 sq ft
As per thumb rule and guidelines, for 500 sq. ft. or (20×25) slab at 4 inch thickness, you will need approximately 6.25 cubic yards of concrete and at 5 inch thickness 7.7 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 500÷80= approx 6.25 cu. yd. and 2) at 5 inch thickness, concrete quantity = 500÷65= approx 7.7 cubic yards.
How many yards of concrete do I need for 600 sq ft
As per thumb rule and guidelines, for 600 sq. ft. or (20×30) slab at 4 inch thickness, you will need approximately 7.5 cubic yards of concrete and at 5 inch thickness 9.25 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 600÷80= approx 7.5 cu. yd. and 2) at 5 inch thickness, concrete quantity = 600÷65= approx 9.25 cubic yards.
How many yards of concrete do I need for 700 sq ft
As per thumb rule and guidelines, for 700 sq. ft. or (20×35) slab at 4 inch thickness, you will need approximately 8.75 cubic yards of concrete and at 5 inch thickness 10.75 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 700÷80= approx 8.75 cu. yd. and 2) at 5 inch thickness, concrete quantity = 700÷65= approx 10.75 cubic yards.
How many yards of concrete do I need for 800 sq ft
As per thumb rule and guidelines, for 800 sq. ft. or (20×40) slab at 4 inch thickness, you will need approximately 10 cubic yards of concrete and at 5 inch thickness 12.5 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 800÷80= approx 10 cu. yd. and 2) at 5 inch thickness, concrete quantity = 800÷65= approx 12.5 cubic yards.
ALSO READ :-
How many yards of concrete do I need for a 30×40 slab
How many yards of concrete do I need for a 20×40 slab
What is the weight of a 30×30 concrete slab
What is the weight of a 50×50 concrete slab
How much does a 10×10 concrete slab weigh
Conclusion:-
As per thumb rule and guidelines, for 1000 sq. ft. or (25 ×40) slab at 4 inch thickness, you will need approximately 12.5 cubic yards of concrete and at 5 inch thickness 15.5 yards of concrete you would required.