How much steel required for 100 sq ft rcc roof slab? Hi guys in this article we know about steel required for 100 sq ft slab 4 inch,5inch and 6 inch thickness.
In RCC slab casting process quantity of steel required for slab is depend on many factors like thickness of slab, type of building structure, residential building, low rise building and construction of high rise building.
Steel required for 100 sq ft slab also depends on load bearing structure and we know that slab transfer its dead load and live load to beam and beam transfer its to column, column transfer load to footing and finally footing transfer load into bed of soil.
There are two types of Steel used in roof slab casting process 1) main rebar & 2) cross bar.
● main rebar :- main reinforcement are used in shortest span of slab that’s why it is also known as shortest rebar, generally main reinforcement are used in bottom of slab have higher dia of steel.
◆ ——— WATCH THIS VIDEO ———
● distribution rebar:- distribution reinforcement are used in longer span of slab that’s why it is also known as longest rebar, generally distribution reinforcement are used in top of slab have lesser dia of steel actually distribution bar put over main bar in opposite direction that’s why it is also known as cross bar.
● Thumb Rule for Steel in RCC slab :-
Generally Thumb Rule for Steel in RCC slab construction is ranging between between 75 Kg to 80 kg per cubic metre per wet volume of concrete of RCC slab.
Steel required for 100 sq ft roof slab
We we have given area of RCC slab is equal to 100 square feet and thickness of RCC slab is 4 inch, 5 inch and 6 inch thick.
● 1) Steel required for 100 sq ft slab 4 inch :- area of RCC slab is equal to 100 square feet and thickness of RCC slab 4 inch,then volume of concrete it is calculated by multiplying area and thickness of slab.
Wet volume of concrete is equal to multiplication of area and thickness of slab 100 sq ft × 4 inch/12 = 33.4 cu ft, so wet volume of concrete equal to 33.4 cu ft.
Now we convert volume of concrete into cubic metre, 1m3 = 35.3147 cuft, then wet volume of concrete in cubic meter = 33.4/35.3147 = 0.944 m3, now volume of concrete is equal to 0.944 m3.
Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 100 sq ft ( 0.944 m3) rcc slab is equal to = 80 × 0.944 = 75.5 Kgs.
Ans. :- 75.5 Kgs steel quantity are required for 100 sq ft 4 inch thick rcc roof slab.
● 2) Steel required for 100 sq ft slab 5 inch :- area of RCC slab is equal to 100 square feet and thickness of RCC slab 5 inch,then volume of concrete it is calculated by multiplying area and thickness of slab.
Wet volume of concrete is equal to multiplication of area and thickness of slab 100 sq ft × 5 inch/12 = 41.7 cu ft, so wet volume of concrete equal to 41.7 cu ft.
Now we convert volume of concrete into cubic metre, 1m3 = 35.3147 cuft, then wet volume of concrete in cubic meter = 41.7/35.3147 = 1.18 m3, now volume of concrete is equal to 1.18 m3.
Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 100 sq ft ( 1.18 m3) rcc slab is equal to = 80 × 1.18 = 94.5 Kgs.
Ans. :- 94.5 Kgs steel quantity are required for 100 sq ft 5 inch thick rcc roof slab.
● 3) Steel required for 100 sq ft roof slab 6 inch :- area of RCC slab is equal to 100 square feet and thickness of RCC slab 6 inch,then volume of concrete it is calculated by multiplying area and thickness of slab.
Wet volume of concrete is equal to multiplication of area and thickness of slab 100 sq ft × 6 inch/12 = 50 cu ft, so wet volume of concrete equal to 50 cu ft.
Now we convert volume of concrete into cubic metre, 1m3 = 35.3147 cuft, then wet volume of concrete in cubic meter = 50/35.3147 = 1.416 m3, now volume of concrete is equal to 1.416 m3.
Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 100 sq ft ( 1.416 m3) rcc slab is equal to = 80 × 1.416 = 113.3 Kgs.
Ans. :- 113.3 Kgs steel quantity are required for 100 sq ft 6 inch thick rcc roof slab.
Now question is how much steel required for 100 sq ft slab ?
● Ans. :- 75.5 kgs, 94.5 kgs & 113.3 Kgs steel quantity are required for 100 sq ft 4 inch, 5 inch & 6 inch thick rcc roof slab.
◆You Can Follow me on Facebook and Subscribe our Youtube Channel
You should also visits:-
1)what is concrete and its types and properties
2) concrete quantity calculation for staircase and its formula
Leave a Reply