How much cement sand & aggregate required for M7.5 concrete

The mix proportion for M7.5 concrete is typically 1:4:8, where 1 is the ratio of cement, 4 is the ratio of sand, and 8 is the ratio of coarse aggregate. This means, for every 1 part of cement, you would need 4 parts of sand and 8 parts of coarse aggregate. The exact quantities would depend on the total volume of concrete you want to produce.

How much cement sand & aggregate required for M7.5 concrete, hi guys in this article we know about how much cement sand & aggregate required per 1m3 of m7.5 grade of concrete & also know about how much cement required for M7.5 concrete & how to calculate cement sand aggregate required for 1 cubic meter of m7.5 grade of concrete.

Different grade of concrete like M25, M20, M15, M10, M7.5 & M5 are nominal mix grade of concrete in which M represent mix and numerical figure 25, 20, 15, 10, 7.5 & 5 are characteristics of compressive strength of concrete gain strength time period of 28 days after curing.

Table 1 :- different grade of concrete and their compressive strength in N/mm2.

different grade of concrete and their compressive strength in N/mm2.
different grade of concrete and their compressive strength in N/mm2.

Understanding grade of concrete:- Grades of concrete are defined by its strength and composition of the concreting material cement sand and aggregate and the minimum strength the concrete should have following 28 days of initial construction. The grade of concrete is understood in measurements of N/mm2 or MPa, where M stands for mix and the MPa denotes the overall characteristics of compressive strength.

Concrete grade types :– there are three types of concrete grade 1) normal grade of concrete, 2) standard grade of concrete& 3) high strength concrete grade. Normal grade of concrete are based on nominal mix ratio of cement, sand and aggregate have comparatively lower compressive strength than standard grade of concrete.

Normal grade of concrete are M25, M20, M15, M10, M7.5 & M5 generally based on nominal mix proportion of cement sand and aggregate.

Standard grade of concrete are M25, M30, M35, M40, & M45 are made according to design mix have higher compressive strength than normal grade of concrete.

High strength concrete grade are M50, M55, M60, M65, & M70 are made according to design mix have higher compressive strength than normal and standard grade of concrete.

According to nominal mix concrete IS456 code book suggest that minimum grade of concrete is M20 which are used for RCC work and M5, M7.5, M10 and M15 are not used for RCC work, generally lower grade of concrete are used in mass concreting, formation of heavy wall, ground filling, retaining wall formation and all PCC work.

Standard grade of concrete and high strength concrete are used to construction of high rise building, industrial building, commercial building, residential building, apartment, Bridge, dams and heavy structure.

Table 2 :- different grade of concrete and its types

different grade of concrete and its types
different grade of concrete and its types

Cement sand and aggregate mix ratio in concrete :– there are two types of mix ratio in in different grade of concrete 1) nominal mix & 2) design mix.

Nominal mix concrete IS456 code book suggest lower and normal grade of concrete like M25, M20, M15, M10, M7.5 & M5 have fix cement sand and aggregate ratio.

Design mix concrete IS 456 code book suggest that standard and high strength concrete grade are made according to different types of considering factor like load bearing structure, earthquake resistance, bending moment of column, Environmental factors and quality of cement sand and aggregate.

Table 3:– grade of concrete types, it’s mix ratio types and mix ratio of concrete.

grade of concrete types, it's mix ratio types and mix ratio of concrete.
grade of concrete types, it’s mix ratio types and mix ratio of concrete.

How much cement, sand and aggregate are required for 1m3 of m7.5 concrete

M7.5 concrete ratio is 1:4:8 by volume. It indicates the nominal ratio of cement, sand and aggregate. It simply means that if 1CFT cement is used for making concrete, you should use 4 CFT sand and 8 CFT aggregate. (i.e. 1 part cement: 4 parts sand: 8 parts aggregate).

M7.5 concrete ratio:- M stand for mix and numerical figure 7.5 is compressive strength of concrete is 7.5N/mm2 for curing time of 28 days and M7.5 concrete ratio is 1 : 4 : 8, mixture of cement, sand and aggregate in which one part is cement, 4 part is sand and 8 part is aggregate or stone mix with water.

Calculating quantity of cement, sand and aggregate required for 1 cubic metre of m7.5 concrete we have given following:-

Wet volume of concrete = 1m3

mix ratio for m7.5 concrete = 1:4:8

We have to do following calculating steps:-

● Step 1 :- we have wet volume of concrete is equal to 1 cubic metre (1m3), but when we calculate actual quantity of dry ingredient cement, sand and aggregate of concrete.

Dry volume of concrete is equal to 1× 1.54 = 1.54 m3 ( cubic meter)

● Step 2 :- m7.5 nominal mix ratio is 1:4:8,in which one part is cement, 4 part is sand & 8 part is aggregate, then total mix proportion is equal to 1+4+8 =13, and part of cement is equal to 1/13, part of sand is equal to 4/13 & part of aggregate is equal to 8/13

How much cement required for M7.5 concrete

● Step 3:- We have dry volume of concrete is equal to 1.54 m3, part of cement in mix = 1/13 and density of cement = 1440 Kg/m3

How much cement required for M7.5 concrete in cubic metre

● Step 4:- calculate cement required for 1 cubic metre of M7.5 concrete in cubic metre is equal to = 1/13 × 1.54 m3 = 0.1185 m3

How much cement required for M7.5 concrete in m3? 0.1185 m3 (cubic meter) of cement are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 0.1185 cubic meters of cement.

How much cement required for M7.5 concrete in Kgs

● Step 5:- calculate cement required for 1 cubic metre of M7.5 concrete in Kgs ( kilogram) is equal to = 1/13 × 1.54 m3 × 1440 Kg/m3 = 171 Kgs

How much cement required for M7.5 concrete in kg?  171 kg of cement are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 171 kilograms of cement.

How many cement bags required for M7.5 concrete

● Step 6:- we know that 1 bag cement weight = 50 kgs,calculate cement bags required for 1 cubic metre of M7.5 concrete is equal to = 1/13 × 1.54 m3 × 1440 Kg/m3/50 = 3.42 bags cement

How many bags of cement required for 1m3 of M7.5 concrete ? 3.42 bags of 50 kg cement are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 3.42 bags of 50kg cement.

How much cement required for M7.5 concrete in cubic feet

Calculate cement required for 1 cubic meter of M7.5 concrete in cubic feet is equal to = 0.1185 x 35.315 = 4.2 CFT.

How much cement required for M7.5 concrete in CFT? 4.2 CFT (cubic feet) of cement are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 4.2 CFT of cement.

CONCLUSION:- How much cement required for 1m3 of M7.5 concrete? 3.42 bags of 50kg, or 0.1185 m3, or 171 kgs of cement are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 4.2 CFT of cement.

How much sand required for M7.5 concrete

We have given dry volume of concrete is equal to 1.54 cubic metre and part of sand in concrete mix is equal to 4/13, density of sand is equal to 1620 Kg/m3 and one cubic metre is equal to 35.3147 cu ft

How much sand required for M7.5 concrete in cubic metre

● Step 7 :- calculate sand required for 1 cubic metre of M7.5 concrete in cubic metre is equal to 4/13 × 1.54 = 0.474 m3

How much sand required for M7.5 concrete in m3? 0.474 m3 (cubic meter) of sand are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 0.474 cubic meters of sand.

How much sand required for M7.5 concrete in Kgs

● Step 8 :- calculate sand required for 1 cubic metre of M7.5 concrete in kgs ( kilogram) is equal to 4/13 × 1.54m3 × 1620 Kg/m3 =786 Kgs

How much sand required for M7.5 concrete in kg? 768 kg of sand are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 768 kilograms of sand.

How much sand required for M7.5 concrete in cft

● Step 9 :- calculate sand required for 1 cubic metre of M7.5 concrete in cft (cubic feet) is equal to 4/13 × 1.54m3/35.3147 × 1620 Kg/m3 = 22 cft

How much sand required for M7.5 concrete in CFT? 22 CFT (cubic feet) of sand are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 22 CFT of sand.

CONCLUSION:- How much sand required for 1m3 of M7.5 concrete? 22 CFT, or 0.474 m3, or 768 kgs of sand are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 22 CFT of sand.

How much aggregate required for M7.5 concrete

We have given dry volume of concrete is equal to 1.54 cubic metre and part of aggregate in concrete mix is equal to 8/13, density of aggregate is equal to 1550 Kg/m3 and one cubic metre is equal to 35.3147 cu ft

How much aggregate required for M7.5 concrete in cubic metre

● Step 10 :- calculate aggregate required for 1 cubic metre of M7.5 concrete in cubic metre is equal to 8/13 × 1.54 = 0.95 m3

How much aggregate required for M7.5 concrete in m3? 0.95 m3 (cubic meter) of aggregate are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 0.95 cubic meters of aggregate.

How much aggregate required for M7.5 concrete in Kgs

● Step 11 :- calculate aggregate required for 1 cubic metre of M7.5 concrete in kgs ( kilogram) is equal to 8/13 × 1.54m3 × 1550 Kg/m3 = 1469 Kgs

How much aggregate required for M7.5 concrete in kg? 1469 kg of aggregate are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 1469 kilograms of aggregate.

How much aggregate required for M7.5 concrete in cft

● Step 12 :- calculate aggregate required for 1 cubic metre of M7.5 concrete in cft (cubic feet) is equal to 8/13 × 1.54m3/35.3147 × 1550 Kg/m3 = 41.5 cft

How much aggregate required for M7.5 concrete in CFT? 41.5 CFT (cubic feet) of aggregate are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 41.5 CFT of aggregate.

CONCLUSION:- How much aggregate required for 1m3 of M7.5 concrete? 41.5 CFT, or 0.95 m3, or 1469 kgs of aggregate are required for 1 cubic meter of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 41.5 CFT of aggregate.

CONCLUSION:- How much cement sand and aggregate required for 1 cubic metre of m7.5 concrete? 3.42 bags of 50 kg (0.1185 m3, 171 kgs) cement, 22 CFT (0.474 m3, 768 kgs) sand & 41.5 CFT (0.95 m3, 1469 kgs) aggregate are required for 1 cubic metre of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 3.42 bags of 50 kg cement, 22 CFT sand and 41.5 CFT of aggregate.

● Table 4 :- cement quantity in bags and kg and aggregate and sand quantity in cubic metre,cubic feet and kg of m7.5 concrete

cement quantity in bags and kg and aggregate and sand quantity in cubic metre,cubic feet and kg of m7.5 concrete
cement quantity in bags and kg and aggregate and sand quantity in cubic metre,cubic feet and kg of m7.5 concrete

Weight of sand & aggregate required for 50 kg cement bag for M7.5 grade of concrete

As we find 3.42 bags of cement,768 kgs sand & 1469 kgs aggregate for 1 cubic metre of m7.5 grade of concrete.

Hence 3.42 bags cement = 768 kgs sand
For 1 bag of cement = 768/3.42= 225 kgs sand

Hence 3.42 bags of cement = 1469 kgs aggregate
For 1 bag of cement = 1469/3.42 = 430 kgs aggregate

225kg of sand and 430 kg aggregate are required per 50 kg bag of cement for m7.5 grade of concrete. Thus, You would need 225kg Sand and 403kg aggregate per 50kg bag of cement to make M7.5 concrete.

How much cement sand & aggregate required for M7.5 concrete
How much cement sand & aggregate required for M7.5 concrete

Volume of sand & aggregate required for 50 kg cement bag for M7.5 grade of concrete

As we find 3.42 bags of cement,22 cft sand & 41.5 cft aggregate for 1 cubic metre of m7.5 grade of concrete.

Hence 3.42 bags cement = 22 cft sand
For 1 bag of cement = 22/3.42= 6.43 cft sand

Hence 3.42 bags of cement = 41.5 cft aggregate
For 1 bag of cement = 41.5/3.42 = 12.13 cft aggregate

6.43 CFT sand & 12.13 CFT aggregate are required per 50 kg of cement bag for m7.5 grade of concrete. Thus, You would need 6.43 CFT Sand and 12.13 CFT aggregate per 50kg bag of cement to make M7.5 concrete.

◆You Can Follow me on Facebook and Subscribe our Youtube Channel

You should also visits:-

1)what is concrete and its types and properties

2) concrete quantity calculation for staircase and its formula

Conclusion:- 

3.42 bags of 50 kg (0.1185 m3, 171 kgs) cement, 22 CFT (0.474 m3, 768 kgs) sand & 41.5 CFT (0.95 m3, 1469 kgs) aggregate are required for 1 cubic metre of M7.5 concrete. Thus, To produce (make) 1m3 of M7.5 concrete you would need 3.42 bags of 50 kg cement, 22 CFT sand and 41.5 CFT of aggregate.

2 thoughts on “How much cement sand & aggregate required for M7.5 concrete”

Leave a Comment