How much cement sand & aggregate required for M10 concrete

The mix proportion for M10 concrete is typically 1:3:6, where 1 is the ratio of cement, 3 is the ratio of sand, and 6 is the ratio of coarse aggregate. This means, for every 1 part of cement, you would need 3 parts of sand and 6 parts of coarse aggregate. The exact quantities would depend on the total volume of concrete you want to produce.

How much cement sand & aggregate required for M10 concrete, hi guys in this article we know about how much cement sand & aggregate required per 1m3 of m10 grade of concrete & also know about how much cement required for M10 concrete & how to calculate cement sand aggregate required for 1 cubic metre of m10 grade of concrete.

Different grade of concrete like M25, M20, M15, M10, M7.5 & M5 are nominal mix grade of concrete in which M represent mix and numerical figure 25, 20, 15,10,7.5 & 5 are characteristics of compressive strength of concrete gain strength time period of 28 days after curing.

Table 1 :- different grade of concrete and their compressive strength in N/mm2.

different grade of concrete and their compressive strength in N/mm2.
different grade of concrete and their compressive strength in N/mm2.

Understanding grade of concrete:- Grades of concrete are defined by its strength and composition of the concreting material cement sand and aggregate and the minimum strength the concrete should have following 28 days of initial construction. The grade of concrete is understood in measurements of N/mm2 or MPa, where M stands for mix and the MPa denotes the overall characteristics of compressive strength.

Concrete grade types :- there are three types of concrete grade 1) normal grade of concrete, 2) standard grade of concrete& 3) high strength concrete grade. Normal grade of concrete are based on nominal mix ratio of cement, sand and aggregate have comparatively lower compressive strength than standard grade of concrete.

Normal grade of concrete are M25, M20, M15, M10, M7.5 & M5 generally based on nominal mix proportion of cement sand and aggregate.

Standard grade of concrete are M25, M30, M35, M40, & M45 are made according to design mix have higher compressive strength than normal grade of concrete.

High strength concrete grade are M50, M55, M60, M65, & M70 are made according to design mix have higher compressive strength than normal and standard grade of concrete.

According to nominal mix concrete IS456 code book suggest that minimum grade of concrete is M20 which are used for RCC work and M5, M7.5, M10 and M15 are not used for RCC work, generally lower grade of concrete are used in mass concreting, formation of heavy wall, ground filling, retaining wall formation and all PCC work.

Standard grade of concrete and high strength concrete are used to construction of high rise building, industrial building, commercial building, residential building, apartment, Bridge, dams and heavy structure.

Table 2 :– different grade of concrete and its types

different grade of concrete and its types
different grade of concrete and its types

Cement sand and aggregate mix ratio in concrete :– there are two types of mix ratio in in different grade of concrete 1) nominal mix & 2) design mix.

Nominal mix concrete IS456 code book suggest lower and normal grade of concrete like M25, M20, M15, M10, M7.5 & M5 have fix cement sand and aggregate ratio.

Design mix concrete IS 456 code book suggest that standard and high strength concrete grade are made according to different types of considering factor like load bearing structure, earthquake resistance, bending moment of column, Environmental factors and quality of cement sand and aggregate.

Table 3:- grade of concrete types, it’s mix ratio types and mix ratio of concrete.

grade of concrete types, it's mix ratio types and mix ratio of concrete.
grade of concrete types, it’s mix ratio types and mix ratio of concrete.

How much cement, sand and aggregate are required for 1m3 of m10 concrete

M10 concrete ratio is 1:3:6 by volume. It indicates the nominal ratio of cement, sand and aggregate. It simply means that if 1CFT cement is used for making concrete, you should use 3 CFT sand and 6 CFT aggregate. (i.e. 1 part cement: 3 parts sand: 6 parts aggregate).

M10 grade concrete ratio is nominally about 1:3:6, (mixture of cement, sand and coarse aggregate) which includes one part of cement, 3 parts of sand and 6 parts of aggregate. And water cement ratio is kept between 0.4 to 0.6.

M10 concrete ratio:- The mix ratio of M10 grade concrete is 1:3:6, consisting of 1 part cement, 3 parts sand (fine aggregate) and 6 parts aggregate (gravel). Apart from that water is used to make the concrete.

M10 concrete ratio for 1 cubic meter is about 1 part cement: 3 parts sand: 6 parts aggregate (1:3:6) are made up of about 222kg (4.44bags of 50kg) cement, 710 kg sand, 1420kg aggregate and about 133 litres of water. This mix ratio used in case plain cement concrete (PCC concrete). And water cement ratio is kept between 0.4 to 0.6.

The nominal mix ratio for M10 grade of concrete is 1: 3: 6, in which one part of cement mix with 3 parts of sand, and 6 parts of aggregate mix with water to gain compressive strength of 10N/mm2 after pouring in desire shape after 28days curing. This means about 222kg (4.44bags of 50kg) cement, 710 kg sand, 1420kg aggregate and about 133 litres of water used to mix to prepare one cubic meter of concrete by taking 1: 3: 6: 0.6 (cement : sand : aggregate : water) nominal mix ratio of concrete.

There are 4.5 bags (0.154 m3, 222 kgs) of 50kg cement, 21 cubic feet (0.462 m3, 998 kgs) sand & 40.5 cubic feet (0.924 m3, 1432 kgs) aggregate are required for 1 cubic metre of M10 concrete.

Calculating quantity of cement, sand and aggregate required for 1 cubic metre of m10 concrete we have given following:-

Wet volume of concrete = 1m3

mix ratio for m10 concrete = 1:3:6

We have to do following calculating steps:-

Step 1 :- we have wet volume of concrete is equal to 1 cubic metre (1m3), but when we calculate actual quantity of dry ingredient cement, sand and aggregate of concrete.

Dry volume of concrete is equal to 1× 1.54 = 1.54 m3 ( cubic meter)

Step 2 :- m10 nominal mix ratio is 1:3:6, in which one part is cement, 3 part is sand & 6 part is aggregate, then total mix proportion is equal to 1+3+6 = 10, and part of cement is equal to 1/10, part of sand is equal to 3/10 & part of aggregate is equal to 6/10

How much cement required for M10 concrete

Step 3:- We have dry volume of concrete is equal to 1.54 m3, part of cement in mix = 1/10 and density of cement = 1440 Kg/m3

How much cement required for M10 concrete in cubic metre

Step 4:- calculate cement required for 1 cubic metre of M10 concrete in cubic metre is equal to = 1/10 × 1.54 m3 = 0.154 m3

How much cement required for M10 concrete in m3? 0.154 m3 (cubic meter) of cement are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 0.154 cubic meters of cement.

How much cement required for M10 concrete in Kgs

Step 5:- calculate cement required for 1 cubic metre of M10 concrete in Kgs ( kilogram) is equal to = 1/10 × 1.54 m3 × 1440 Kg/m3 = 222 Kgs

How much cement required for 1m3 of M10 concrete in kg? 222 kg of cement are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 222 kilograms of cement.

How many cement bags required for M10 concrete

Step 6:- we know that 1 bag cement weight = 50 kgs,calculate cement bags required for 1 cubic metre of M10 concrete is equal to = 1/10 × 1.54 m3 × 1440 Kg/m3/50 = 4.44 = 4.5 bags cement

How many cement bags required for M10 concrete? 4.5 bags of 50kg of cement are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 4.5 bags of 50 kilograms of cement.

How much cement required for M10 concrete in cubic feet

Calculate cement required for 1 cubic meter of M10 concrete in cubic feet is equal to = 0.154 x 35.315 = 5.44 CFT.

How much cement required for M10 concrete in CFT? 5.44 CFT (cubic feet) of cement are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 5.44 CFT of cement.

How much cement required for 1m3 of M10 concrete? 4.5 bags of 50kg cement or 0.154 m3, or 222 kgs of cement are required for 1 cubic meter of M10 concrete. To produce (make) 1m3 of M10 concrete you would need 4.5 bags of 50 kilograms of cement.

How much sand required for M10 concrete

We have given dry volume of concrete is equal to 1.54 cubic metre and part of sand in concrete mix is equal to 3/10, density of sand is equal to 1620 Kg/m3 and one cubic metre is equal to 35.3147 cu ft

How much sand required for M10 concrete in cubic metre

Step 7 :- calculate sand required for 1 cubic metre of M10 concrete in cubic metre is equal to 3/10 × 1.54 = 0.462 m3

How much sand required for M10 concrete in m3? 0.462 m3 (cubic meter) of sand are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 0.462 cubic meters of sand.

How much sand required for M10 concrete in Kgs

Step 8 :- calculate sand required for 1 cubic metre of M10 concrete in kgs ( kilogram) is equal to 4/10 × 1.54m3 × 1620 Kg/m3 = 998 Kgs

How much sand required for 1m3 of M10 concrete in kg? 998 kg of sand are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 998 kilograms of sand.

How much sand required for M10 concrete in cft

Step 9 :- calculate sand required for 1 cubic metre of M10 concrete in cft (cubic feet) is equal to 3/10 × 1.54m3/35.3147 × 1620 Kg/m3 = 21 cft

How much sand required for M10 concrete in CFT? 21 CFT (cubic feet) of sand are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 21 CFT of sand.

How much sand required for 1m3 of M10 concrete? 21 CFT or 0.462 m3, or 998 kgs of sand are required for 1 cubic metre of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 21 CFT of sand.

How much aggregate required for M10 concrete

We have given dry volume of concrete is equal to 1.54 cubic metre and part of aggregate in concrete mix is equal to 6/10, density of aggregate is equal to 1550 Kg/m3 and one cubic metre is equal to 35.3147 cu ft

How much aggregate required for M10 concrete in cubic metre

Step 10 :- calculate aggregate required for 1 cubic metre of m10 concrete in cubic metre is equal to 6/10 × 1.54 = 0.924 m3

How much aggregate required for M10 concrete in m3? 0.924 m3 (cubic meter) of aggregate are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 0.924 cubic meters of aggregate.

How much aggregate required for M10 concrete in Kgs

Step 11 :- calculate aggregate required for 1 cubic metre of M10 concrete in kgs ( kilogram) is equal to 6/10 × 1.54m3 × 1550 Kg/m3 = 1432 Kgs

How much aggregate required for 1m3 of M10 concrete in kg? 1432 kg of aggregate are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 1432 kilograms of aggregate.

How much aggregate required for M10 concrete in cft

Step 12 :- calculate aggregate required for 1 cubic metre of M10 concrete in cft (cubic feet) is equal to 6/10 × 1.54m3/35.3147 × 1550 Kg/m3 = 40.5 cft

How much aggregate required for M10 concrete in CFT? 40.5 CFT (cubic feet) of aggregate are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 40.5 CFT of aggregate.

How much aggregate required for 1m3 of M10 concrete? 40.5 CFT, or 0.924 m3, or 1432 kgs of aggregate are required for 1 cubic metre of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 40.5 CFT of aggregate.

How much cement sand and aggregate required for 1 cubic metre of m10 concrete? 4.5 bags of 50kg (0.154 m3, 222 kgs) cement, 21 CFT (0.462 m3, 998 kgs) sand & 40.5 CFT (0.924 m3, 1432 kgs) aggregate are required for 1 cubic meter of M10 concrete. Thus, To produce (make) 1m3 of M10 concrete you would need 4.5 bags of 50kg of cement, 21 CFT sand and 40.5 CFT of aggregate.

● Table 4 :- cement quantity in bags and kg and aggregate and sand quantity in cubic metre, cubic feet and kg of m10 concrete

cement quantity in bags and kg and aggregate and sand quantity in cubic metre,cubic feet and kg of m10 concrete
cement quantity in bags and kg and aggregate and sand quantity in cubic metre,cubic feet and kg of m10 concrete

Weight of sand & aggregate required for 50 kg cement bag for M10 grade of concrete

As we find 4.5 bags of cement, kgs 998 sand & 1432 kgs aggregate for 1 cubic metre of m10 grade of concrete.

Hence 4.5 bags cement = 998 kgs sand
For 1 bag of cement = 998/4.5= 222 kgs sand

Hence 4.5 bags of cement = 1432 kgs aggregate
For 1 bag of cement = 1432/4.5 = 318 kgs aggregate

222 kg of sand and 318 kg aggregate are required per 50 kg bag of cement for m10 grade of concrete. Thus, You would need 222kg Sand and 318kg aggregate per 50kg bag of cement to make M10 concrete.

How much cement sand & aggregate required for M10 concrete
How much cement sand & aggregate required for M10 concrete

Volume of sand & aggregate required for 50 kg cement bag for M10 grade of concrete

As we find 4.5 bags of cement, 21 cft sand & 40.5 cft aggregate for 1 cubic metre of m10 grade of concrete.

Hence 4.5 bags cement = 21 cft sand
For 1 bag of cement = 21/4.5= 4.67 cft sand

Hence 4.5 bags of cement = 40.5 aggregate
For 1 bag of cement = 40.5/4.5 = 9 cft aggregate

4.67 CFT sand & 9 CFT aggregate are required per 50 kg of cement bag for m10 grade of concrete. Thus, You would need 4.67 CFT Sand and 9 CFT aggregate per 50kg bag of cement to make M10 concrete.

◆You Can Follow me on Facebook and Subscribe our Youtube Channel

You should also visits:-

1)what is concrete and its types and properties

2) concrete quantity calculation for staircase and its formula

Conclusion:

4.5 bags of 50kg (0.154 m3, 222 kgs) cement, 21 CFT (0.462 m3, 998 kgs) sand & 40.5 CFT (0.924 m3, 1432 kgs) aggregate are required for 1 cubic meter of M10 concrete.

M10 concrete ratio:- The mix ratio of M10 grade concrete is 1:3:6, consisting of 1 part cement, 3 parts sand (fine aggregate) and 6 parts aggregate (gravel). Apart from that water is used to make the concrete.

8 thoughts on “How much cement sand & aggregate required for M10 concrete”

  1. Hello I didn’t get answers for this please help me to finding solutions for this question?
    1.For a certain grade of concrete, the ratio of Cement: Sand: Aggregate is 1: 3: 6 (by volume). If 0.33 cu.m. of sand is used, what is the combined sum of the volumes of cement and aggregate?

    Reply
  2. Please check the quantity calculation of sand for M10
    There is 4/10*1.54*1620 but right calculation is 3/10*1.54*1620
    Quantity is 997 kg but right quantity is 748 kg

    Reply
  3. the multiplication for aggregate (1.54), I dont think it should be because aggregate does not shrink. cement and sand shrinks when water is added

    Reply

Leave a Comment